Construction Information

Road Repair and Street Safety

The following are several Road Repair and Street Safety related projects currently being developed with construction anticipated to begin in 2017:

  • Chip Seal Program on the west side of Flagstaff
    • Construction anticipated to start spring 2017
  • Overlay Program on the west side of Flagstaff
    • Construction anticipated to start spring 2017
  • Lockett Rd. (Patterson Blvd. to Fanning Dr.) - Project Manager: Trevor Henry, (928) 213-2684, thenry@flagstaffaz.gov
    • Construction anticipated to start April 17, 2017

  • Zuni Dr. (Lake Mary Rd. to Open Channel) - Project Manager: Randy Groth, (928) 213-2683, rgroth@flagstaffaz.gov
    • Construction started March 6, 2017 and may continue to mid-November 2017
    • Currently installing utilities on Zuni Dr. between Lake Mary Rd. and Walapai Dr.

  • Beaver St. (Columbus Ave. to Birch Ave.) - Project Manager: Eli Reisner, (928) 213-2679, ereisner@flagstaffaz.gov
    • Phase 1 Utility Improvements, Columbus to Sullivan the 12" Water Main, Water and Sewer Services have been installed. 
    • Phase 2 Surface Improvements, construction beginning July 31, 2017 from Columbus to Hunt. 
    • (Phase1) August 2017, installing a 12" Water Main, Water and Sewer Services, and Electrical Conduit from Sullivan to Elm and installing 8" Sewer Main from Elm to Dale.

  • Dale Ave. (Humphreys St. to Agassiz St.) - Project Manager: Eli Reisner, (928) 213-2679, ereisner@flagstaffaz.gov
    • (Phase 1) Dale/Beaver intersection construction anticipated to begin August of 2017
    • (Phase 1) The majority of Dale Ave. construction is anticipated to begin October 2017 and will start at Humphreys St.

Please check back periodically for construction updates.
Here is an interactive map with Road Repair and Street Safety project information.



Additional information, including the status of Street Reconstruction Projects

Maps of the scheduled improvements and reconstruction projects can be found on the City’s website: Link to Maps
Notification & keeping you informed:

Residents and businesses have been notified of the work and project signs are up. The public should expect traffic impacts in all areas throughout the week. The much needed road repairs will likely result in some temporary traffic restrictions, noise and dust. Every attempt will be made to maintain access to businesses and residences. The City apologizes for any inconveniences caused by the work. We appreciate the community’s investment in our critical infrastructure and the public’s cooperation. This work is scheduled for daytime hours and City contractors and instructed to keep impacts as minimal as possible. Please note that construction areas inherently have many hazards as a result citizens and visitors should stay clear of construction sites. Signs are posted warning people not to enter the construction area in order to keep pedestrians and bicyclists from getting too close to work activities and deter the passerby who might be curious about the project from entering the space after work hours. Follow the posted signs to keep yourself safe and avoid an accident.
This work is part of the voter approved Prop 406 dedicated sales tax for road repair and street safety improvements, more than $100 million of infrastructure improvements scheduled to be completed over the next 20 years.
The City is committed to keeping our promise to our citizens to touch every street in Flagstaff and to keep everyone informed on the status of the project work. The City will send updates to local media, and will post these updates on the City website at www.flagstaff.az.gov/roadsafety, and on the City Facebook page.