Fir Avenue Water Main Replacement

Project Overview

The general project scope includes demolition work, installation of 3,062 LF of new water main, 26 water services, 6 fire hydrants, match up asphalt for pavement patches, concrete curb and gutter, concrete driveway approaches and sidewalks. This project is part of the City’s ongoing infrastructure replacement program.

  • Cost: $577,804 plus contractor allowance of $43,335.30
  • Location: Mesa Drive and Fir Avenue in the Mt. Elden Park Subdivision, north of Flagstaff Medical Center
  • Project Manager: Trevor Henry
  • Timeline: June 2020 – October 2020
  • Contractor: Mountain High Excavation

_____________________________________________________________________________________________________________

2020 Periodic Updatesconstruction fir avenue

August:

  • 8” waterline installation continues in Mesa Drive.
  • Approximately 850 feet has been installed with backfill.
  • Associated water service taps have been installed on the new main along Mesa Dr.

July:

  • Notice to Procced was issued for July 6, 2020.
  • Mountain High Excavating setup traffic control for the project construction area.
  • Potholing efforts and pre-construction investigation are underway.
  • All residents have been contacted by the project team.